Tracking Activity Links

J Venkatesh PMP PSP ACIArbMember for 20 years 2 months
Created
3
1
0
Dear Planners,

I want to check/track the changes made in the activity links between the original and revised program...

The idea, am trying is exporting the predecessor / successor details of both the programs in to WK1 / Excel format and make a comparison check of the successor/predecessor columns of both the programs using excel functions..

but in reports, the precessor/suceessor can be viewed as Act Id*, Act Id* like that only...I mean, the predecessor/successor activity is shown with * mark only, not with the type of link and with the lag days...

Is there any option to see the links like Act Id SS+__ days, Act Id FS+ __ days (The link as per the program) the way we can see in MS Project..

Venkat

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    Try "Tools / Project Utilities / Export" and check the "export successor relationships" radio button on the content page. Good luck!
  2. 0
    Dieter Wambach ·
    Hi Venkat,

    if you look into the P3 example project, there is a prepared export EX12.

    Or you create a new one: "ADD" --> enter the different criteria --> Under the detail tab "Content" select the radio button Successor relationship.

    I hope, this will work

    Dieter
  3. 0
    J Venkatesh PMP PSP ACIArb ·
    Ronald and Dieter

    Thanks a lot...

    Venkat

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?