problems in combining schedules
In the Open Standard
Greg SwartzMember for 19 years 2 months
- Created
- 2
- 1
0
I have submitted a schedule that has been incorporated into a "master" schedule. The problem is that when the master scheduler calculates the schedule, it shifts all of my non-complete activities out by months, and assigns 500-600 days of float. What parameters can I suggest to the master scheduler to ensure that my schedule is intact? On the returned copy, I have tried zeroing the float, constraining the EF’s, changing percent completes, changing the OD’s with no effect. Is it locked and only a pretty picture?