Skip to content

Project Percent complete

Zameer JeffMember for 19 years 5 months
Created
7
1
0
Hello friends

I get schedule reports but I do not know how to get a report which tells how much percentage of whole project is completed.


Thanks

7 replies

Oldest first
  1. 0
    A D ·
    For the overall project - percent complete, take the LEVEL 1 print-out. Its a part of monthly report submission in most of the orgz’s.

    In the percent complete column, it will show % complete.

    In the footer, (If the finish date is not imposed) it will show the updated completion date.

    Cheers,
  2. 0
    Ulysses Garcia ·
    Ravi has answer your question in some sort, im in doubt if it meets your needs.
    You need to present your report to expect the audience to undestand.
    first,make a baseline in p3 as target, then decide what algorithm to compute % complete, is it physical, unit, or duration, allocate either MH or cost. the go to menu.. report > cost/resources,then print
    i hope it helps
    regards.

  3. 0
    Pranab Kumar Deb ·
    hello zameer,
    Use format>organize>work break down , and then select Top in total , u should be getting the subtotal at the highest wbs level for percent complete ,
    regards
    deb
  4. 0
    Alexandre Faulx-Briole ·
    Zameer,
    you should 1st create a wbs structure where Level 1 is the whole project,
    then organize the layout to show the workbreakdown, and display the total for the 1st level
    Alexandre
  5. 0
    Zameer Jeff ·
    Thanks for your help guys.

    I am working on Pranab option to get a percent complete report for the project .when I go to organize in group by column I have Level 1, Level 2 and level 3.
    Please let me know that in Total column do I have to select “Top” for all three levels(Level 1, Level 2 and Level 3)

    Thanks
  6. 0
    Pranab Kumar Deb ·
    Hello Zameer ,
    That depends on how you want to see the total percent complete , if u want to see in all the levels , then u have to select top in all the levels , if you want to see the total complete of the project then u have to select "top" only in the topmost level.
    HTH
    Deb
  7. 0
    Anoon Iimos ·
    make sure that you understand how your Percent Complete was reckoned

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?