P3 Error #88

Ife OlykeMember for 19 years 8 months
Created
1
1
0
Hi everyone,

My P3 crashed when I tried importing some activities into the plan. I thought it will be a good idea to back up the plan before trying the import again. When i tried backing up the plan, i got the error message below and my P3 crashed again;

.ACT file not found. error #88

Has anyone ever experienced this? Any helpful ideas will be most appreciated.

Cheers.

Ifeanyi

1 reply

Oldest first
  1. 0
    Karen Smith ·
    Hi Ifeanyi,

    Go to your files see if there is an .ACT file I assume not or it’s corrupt. Go to your previous revision copy the .ACT file into your schedule that crashed and that should fix the problem.
    Cheers.
    Karen