P5 Project group export issues to P3

Kevin MatthewsMember for 20 years 4 months
Created
2
20
0
G’day,

I am being forced to use P5 and P3 and import/export between the two versions. I have set up 3 projects in P5 as a project group but can only export these as stand alone projects into P3; rather than as part of a project group.

Any ideas ?

Thanks,

Kevin.

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Kevin

    You can copy a project group as a project into another project group. It will be possible to export the three P5-Projects to P3. You’ll have 3 project groups. Then copy those P3-projects into a fourth (new) Project. To this for the complete life of your projects will be a horror.
    It is a break of structures. In any case you’ll loose informations.
    Maybe another solution will help: I suppose, planners in construction area want to keep their old P3 and reporting has to be done in P5. In such cases -if it’s not possible to convince old planners that a common solution is better, I let them schedule in P3, import with "update" into P5 and do the reporting. Import then only will be one-way and with reliable results.
    Regards
    Dieter
  2. 0
    Kevin Matthews ·
    Thanks Dieter,

    Keep Planning.

    Kevin.