input of actual site manhours to P3
In the Open Standard
Ali KandemirMember for 21 years
- Created
- 1
- 1
0
Dear all,
Pls inform me if there is any way to track productivity rates in P3. I m using excel sheet for this so far. For each activity in schedule, i get earned manhour vales from P3 based on percentage complete. and i input this to excel sheet on the related activity column. Actual manhours are coming from site timekeeper to whom i declared all activities and their descriptions. so i can calculate productivity rate with the ratio of actual manhours to earned manhours.
As far as i know, there is no problem to calculate earned value when i input percentage complete, P3 automatically calculates, but as for the actual manhour there is the only way to get this infrmation is site timekeeper.
But the point is can i input actual manhours to P3, and does it calculate the ratio between earned manhour and actual manhour.
Pls inform me if there is any way to track productivity rates in P3. I m using excel sheet for this so far. For each activity in schedule, i get earned manhour vales from P3 based on percentage complete. and i input this to excel sheet on the related activity column. Actual manhours are coming from site timekeeper to whom i declared all activities and their descriptions. so i can calculate productivity rate with the ratio of actual manhours to earned manhours.
As far as i know, there is no problem to calculate earned value when i input percentage complete, P3 automatically calculates, but as for the actual manhour there is the only way to get this infrmation is site timekeeper.
But the point is can i input actual manhours to P3, and does it calculate the ratio between earned manhour and actual manhour.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?