Dragging activity bar

Mangesh KhuspeMember for 19 years 6 months
Created
2
1
0
hi
all in some projects i can move the activity bar to any new position i want, but in some i cant use this facility. The cursor does not change to plus sign and hence does not allow the dragging of the bars, but in some projects it does.
whats causing this?

regards
mangesh

2 replies

Oldest first
  1. 0
    Marc Borburgh ·
    Hi Mangesh,

    This option is only available to the key bar. Check your bar settings and make sure you try to move the key bar.
  2. 0
    Mangesh Khuspe ·
    Thanks
    marc
    the problem has been solved

    regards
    mangesh