Activity Limit Exceeded

Adelfa SapinosoMember for 19 years 2 months
Created
4
1
0
hello there,

i tried to copy my p3 file from my laptop & save the same to another pc but when i opened the copied file, it said "activity limit exceeded".

got confused since i could open the "original" from my laptop while i couldn’t with the other pc. tried re-installing but still didn’t work.

i couldn’t figure it out why...kindly extend your advice...

thanks in advance!

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    It seems, that on the target computer Suretrack (some kind of "Primavera Light") is installed and not P3.
    Dieter
  2. 0
    Pinan T. ·
    maybe the one installed in the laptop is the unlimited version or licensed while the one you installed in the PC is the limited one or demo
  3. 0
    Shahzad Munawar ·
    Demo Version usually has limited activities. You need to install the Licensed Version so that you can easily carry out your planning for unlimited activities without any such problem.
  4. 0
    Adelfa Sapinoso ·
    thank you so much! now everything’s clear.. :)

    regards!