Resource Loading !
In the Open Standard
Deepak JainMember for 20 years 9 months
- Created
- 4
- 1
0
Please advice on below mentioned scenario :-
Three men were required to complete a 3 day long activity, and all three resources would be utilised every day. If I define 3 units (Men) per day in P3, it calculates the BQ as 9 men and this will be reflected onto Resource Histogram (Over - Resourced). And if i gave a BQ value as 3 , then Units/day bcome 1 which is under -resourced. Pls suggest How to input this correctly?
Three men were required to complete a 3 day long activity, and all three resources would be utilised every day. If I define 3 units (Men) per day in P3, it calculates the BQ as 9 men and this will be reflected onto Resource Histogram (Over - Resourced). And if i gave a BQ value as 3 , then Units/day bcome 1 which is under -resourced. Pls suggest How to input this correctly?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?