Resource Salary

Ömer Faruk ÖZBERKMember for 19 years 1 month
Created
1
1
0
i have some activities which will be completed in a time interval and each of them has the same resource (labor).
but this labor works for a salary and it is not important how many activities does he/she involves at the end of the month he/she will be paid same amount of money. how can i assign this resource to the subjected activities.

thanks.

1 reply

Oldest first
  1. 0
    David Kelly ·
    In order to put fixed costs into the plan you should put the PRICED version of the resource against a hammock activity. Remember the "Freeze resource units per time period" switch in the autocost rules.

Log in or join to reply