Skip to content

Resource Curves

Kevin DonaghyMember for 23 years 4 months
Created
0
2
0
Hi planners,

I have a level one schedule, that I have used resource curves on, seeing I don’t have the detail to get a resource histogram that is not linear.

When I made a copy of the schedule, the resource curves have disappeared, so I added the one I was using, but now nothing happens to the resource curve, it remains linear.

Any one with suggestions / ideas?

I know using a resource curve is a quick fix, but I don’t have the detail to develope a full schedule.

Thanks, Kevin, Perth Australia

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?