Calendars in P3

John WishartMember for 23 years 4 months
Created
2
1
0
Experiencing problems when trying to set up hourly calendars for a long period, 1 year, Jan 2008 till 31st Dec 2008. After a while P3 shuts down and the computer needs to be re-booted to open P3 again. Further attempts to develop the calendar results in the same problem. Is anyone aware of this, and what the solution is?

2 replies

Oldest first
  1. 0
    Kevin Donaghy ·
    Hi John,

    Might be a silly question, but if your schedule is a year, why are you doing it in hours?

    I have done shutdowns in hours, but mostly all in days.

    Kevin
  2. 0
    John Wishart ·
    Good question, it’s a programme of major machinery overhauls, gas turbines and compressors, which spans 10 months. Each machine overhaul works 24 hours round the clock. Agree that it is normally only shutdowns planned in hours taking a few weeks at the most.

Log in or join to reply