Relationships and its impacts
In the Open Standard
Khawaja UddinMember for 20 years 8 months
- Created
- 3
- 1
0
Dears ,
After incorporating MEP programs in given civil program of works ...we reached to certain project completion date .
Later on due to some reasons we tried to pull back proj.comp.date .......to do this we started crashing the critical path ..by reducing the duration of activity ...when the duration is changed ....proj.comp.date moved ahead rather falling earlirer.
The program file contains variety of relationship like FS,SS & FF .
If some one ,also have observed the same .....please clarify the reasons
Thanks
Ehtisham
After incorporating MEP programs in given civil program of works ...we reached to certain project completion date .
Later on due to some reasons we tried to pull back proj.comp.date .......to do this we started crashing the critical path ..by reducing the duration of activity ...when the duration is changed ....proj.comp.date moved ahead rather falling earlirer.
The program file contains variety of relationship like FS,SS & FF .
If some one ,also have observed the same .....please clarify the reasons
Thanks
Ehtisham
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?