Histogram- Resource
In the Open Standard
Ranganathan RangaswamyMember for 19 years 2 months
- Created
- 4
- 1
0
Can some one guide me for Histogram
take for eg an activity which has
BQ -3000hrs
Duration-15days
there fore units per day will be 3000/15= 200hrs
If people work 10hrs per day then the # of people require will be 200/10=10
Now i want to create a histogram with time in x axis and # of manpower required in Y axis
I go to Tools-Graphic Reports- Resource and Cost Graphics-Histogram with Ordinal rates-content-
If I go there only Show data :Resource or Cost is only available
we know Resource which is BQ
I want Show data as Units per day where i can divide by 10 to get # of People
Can some one help
take for eg an activity which has
BQ -3000hrs
Duration-15days
there fore units per day will be 3000/15= 200hrs
If people work 10hrs per day then the # of people require will be 200/10=10
Now i want to create a histogram with time in x axis and # of manpower required in Y axis
I go to Tools-Graphic Reports- Resource and Cost Graphics-Histogram with Ordinal rates-content-
If I go there only Show data :Resource or Cost is only available
we know Resource which is BQ
I want Show data as Units per day where i can divide by 10 to get # of People
Can some one help
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?