Split bars

Moutaz AldeibMember for 22 years 10 months
Created
2
15
0
Dear Planners,

I would like to creat a schedule, how to split the bar into many bars for one activity.

2 replies

Oldest first
  1. 0
    Paul Harris ·
    Create many activities, P3 does not have a split function like MSP.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Pranab Kumar Deb ·
    Hello Moutaz,
    I believe you can achieve your requirement with WBS , the WBS will be the main Activity and the lower level will be the constituent sub activities which will make up the WBS.
    regards
    Deb

Log in or join to reply