Average Resource Curve in Layout

Renjith BMember for 20 years 11 months
Created
1
1
0
Dear Planners,

Is any body know how to show the average Curve/Histogram in the resource/ cost profiles

regards
renjith

1 reply

Oldest first
  1. 0
    Johny Kesserwany ·
    In Resource/Cost graphics report:

    Choose ’Content’:
    Under Histogram
    Use/cost choose ’Average’

    Regards
    JK

Log in or join to reply