Dear Planners,

In Budget Summary dialog box, the Planned Value is not as the Budget amount, what is the difference?

Another question, in the same dialog box the variance in cost is zero eventhough the earned value and actual to date figures are not the same.

The above example is taken from the project "ENGR" activity "D1070".

Regards,

Moutaz

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    msah el kheir moutaz,
    it certainly means that the activity specifics have been changed since the target was saved, and the target was not updated
    look at the preceeding activities, the values are not correct there either.
    bqa 3ala kheir,
    Alexandre