Page Setup in Suretrak

Malena MorónMember for 18 years 8 months
Created
1
1
0
Hello all!

This is my first post in the forum and I have a such a problem with this.....

I’m still working with Suretrak as so does my Company...

Once I have created a Project in Suretrak, have updated it for several times, and added new activities that increase the time for the Project.... I find that I cannot Update the Page Setup...

I can open this window, change anything I want, but, when I click on OK, it doesn’t work... Simply makes nothing.

And there’s no way it works until I click on CANCEL.

Can anybody help me, please?

Thanks a lot!

1 reply

Oldest first
  1. 0
    Ronald Winter ·
    My guess is that you have deleted, moved, or renamed your associated graphic file. Look under the Header or Footer tabs and see if you have a graphic file listed there in one of the sections. If it no longer exists, you will generate the type of error that you are seeing on trying to exit.

    Good luck!