Data date

Kumar IMember for 23 years 3 months
Created
3
2
0
ASSUME I collect progress till 31 march2008 and update actuals by the evening of the same day what is the data date 31march or 1st april in p3

3 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·
    Dear Kumar,
    The Data date should be 1st April , since you have already updated progress upto 31st March, you should let the software schedule from the 1st of April.
    regards
    deb
  2. 0
    A D ·
    1st of April, as data entered is upto 31st March
  3. 0
    Kieran Thomson ·
    Primavera reads days from midnight upto 1 minute before midnite, therefore if you input progress for a day, you should set the data date as the next day as this is a new day. Confused? Thik of it this way....

    Day 1 starts today, client asks for report on todays work, we cannot progress upto day 1 as it is past tense therefore we use the next working day.

    Still confused?