fragnet and copy

Moutaz AldeibMember for 22 years 9 months
Created
3
1
0
Dear Planners,

What is the difference between using fragnet and copy?

Regards,

Moutaz

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Moutaz,
    fragnet lets you build a larger project from smaller parts; you will 1st create small projects for every work package of the final larger project, then save individually as fragnets; 2nd, you will open a new blank project and import (retrieve) any necessary fragnet
    copy a project is used to create a new project from an existing one; you could copy project A to project B and then delete any unnecessary activity, and the result would be close to the use of fragnets
    Hope it helps,
    Alexandre
  2. 0
    Moutaz Aldeib ·
    Thanks Alexander,

    It helps me too much, but the results are the same in terms of durations and relationships.

    Regards,

    Moutaz
  3. 0
    Imran Malik ·
    Well fragnet is available globally to you whenever you need; while copy is simple function for clipboard only