Hi,Guys

I am using P3 and it has got different calenders like 5 days and 6 days, and it has so many constraints due to delivery slippage.

Now the question is "which is the best CPM TF=0 or Longest path".

Appreciate your responce.

And lastly how the filter works in P6 TF or Longest path

Thanks

Salah

1 reply

Oldest first
  1. 0
    James Barnes ·
    Longest path has a chequered reputation in P3.1, I don’t have much experience with it but understand that it doesn’t exactly work as advertised.

    I use TF=0.

    Actually, if you have several "near critical" paths you can go to Tools/options/critical activities and set this to a larger number, I plan in hours and usually set critical activities to be TF<10 hours for critical paths and TF<50 hours to highlight near critical mass work.

Log in or join to reply