Dear planners

Could any one explain how to record actual resources consumed for activities.

Suppose an acvity having a duration of 15days and it has multiple resources like pipe fitters and millwright, at the time of budgeting the resources allocated were 75 pipe fitters and 75 millwright.

Now the question is how to record on daily basis how many PF and MW were used as actual consumptions and how to represent in tabular report and in graphical report. I am updating progress end of each week.

Thanks in advance

Salah

3 replies

Oldest first
  1. 0
    Pinan T. ·
    get it from daily TIMESHEETS from ur Timekeeper..

    Use Excel Charts for Comparison
  2. 0
    Salahuddin Ahmed ·
    Pinan,

    Thanks for your reply.

    Still my question is how do i enter data in P3 and generate tabular and graphical report.

    Pipe fitter Mon - Fri 5*8= 40
    Millwright Mon - Fri 5*8= 40

    I am recoding progress every week and the reports to be submitted every Monday.

    Appreciate help.

    Salah
  3. 0
    Pinan T. ·
    you can record actuals in resource window, and store period performance

    but im not sure if p3 reports can generate actual quantities graph and loading, only current and planned will be shown as far as i know

    do it in excel