Resource Leveling??????
In the Open Standard
Sajid BalmaMember for 19 years 4 months
- Created
- 3
- 1
0
Dears
I am a bit confused on this issue. Following are excerpts of the books on this and its confounding the confusion for me.
P3 Planning & Control Guide
Quote
Resource leveling does not change activity durations or resource requirements; it can, however, delay schedule dates. (Page 105)
Unquote
now from
P3 Reference Manual
Quote
In addition to delaying activities until resources are
available, P3 can decrease the overall duration of an independent (or meeting) activity during resource leveling. (Page 230)
Unquote
Is it not contradictory info or am I missing something?
I am a bit confused on this issue. Following are excerpts of the books on this and its confounding the confusion for me.
P3 Planning & Control Guide
Quote
Resource leveling does not change activity durations or resource requirements; it can, however, delay schedule dates. (Page 105)
Unquote
now from
P3 Reference Manual
Quote
In addition to delaying activities until resources are
available, P3 can decrease the overall duration of an independent (or meeting) activity during resource leveling. (Page 230)
Unquote
Is it not contradictory info or am I missing something?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?