How to restrain partial access?

Safak VuralMember for 18 years 5 months
Created
2
2
0
Dear all,
I am willing to load many resources to my project file in order to make some cost estimations but i dont want to share these information with mt Client when issuing PRM backup file as weekly progress. Is there any way to keep this kind of information to be accessible only by me?(Note: My file have to include some resources but i want to restrain some resources and cost accounts only.)

Thanks

Safak VURAL

2 replies

Oldest first
  1. 0
    Gün Göksu ·
    technically, If the data is in the files. everyone can read it.

    you could take a copy each week (you should anyway) and use global change to remove the resources you dont want seen. and send this to the client.

    :)

  2. 0
    Safak Vural ·
    Thanks