P3 ERROR

Hemanth KumarMember for 23 years 11 months
Created
2
1
0
Hi
Recently i importrd a project from p5 to p3
now in p3 all activities behaves like MS Project
when i move activities the activities stays there after scheduling , no logic or relationship is working
anybody has any experiance this ?
my all other projects in p3 is fine

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    remove constraints (if any)
  2. 0
    Ronald Winter ·
    Hemanth,

    This sometimes occurs if the P5 schedule being exported had relationships to other schedules. When you export such a schedule, I believe that the process adds constraints to activities to make up for the missing relationships. Look to the constraints. Good luck!