question:import the xer file

Liu YiMember for 18 years 11 months
Created
3
1
0
when I import the .xer to P6,only the 29o4KB file cann’t be imported.but the 2006KB’s file can be.why? the promption is :an applicantion event has been intercrepted,please note the event code for reference .event code :AVAA0-3746-4.
thanks!

3 replies

Oldest first
  1. 0
    Wael Abdelfattah ·

    I'm having the same problem.

    I'm having the same problem. The only solution I came up with, is to start a new database with a new connection and then import all projects all over again.

  2. 0
    Zoltan Palffy ·

    make sure that you have the

    make sure that you have the correct java version that it is working.

  3. 0
    Tommy James Nuneza ·

    Hello, I have problem in

    Hello,

     

    I have problem in importing xer p6 file.

    Error occur "CVRCU-1939-9 Default value  provided for field ev_compute_type is not valid"

    Thank you in advance for your input.

     

    COCOY