Skip to content

Data Date

Brad RicheyMember for 18 years 4 months
Created
0
2
0
All

My project has a data date of June of 08, and after that I entered a new activity without a predecessor expecting the early start date to be the Data date. However when I scheduled the project in the system it is pulling the ES back to May 08. Even when I enter an actual date and change the RD the EF date is not correct. I have checked the Project Overview for the data date just to be sure, I also checked for any constraints and restarted the system and tried it again with a different new activity. As I said it is a new activity, Please Help

Thanks Brad

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?