Activity cannot finish until another - zero float
In the Open Standard
Smithie JohnnyMember for 18 years 5 months
- Created
- 3
- 3
0
I am trying to work out how to drive logic within schedule to be finish dependent. That is the activity must finish when another activity is 50% finished, but that is has zero float between the activity finishign and the other one being 50% completed?
Like the idea of JIT -- "just in time": so the car seat gets manufacturered in a timeframe driven by when it needs to be assembled into the car, so that ther is zero float between the seat arrives onsite at the car factory, and the seat needs to be installed into the car.
How do i set up P3 to deliver this outcome???
Like the idea of JIT -- "just in time": so the car seat gets manufacturered in a timeframe driven by when it needs to be assembled into the car, so that ther is zero float between the seat arrives onsite at the car factory, and the seat needs to be installed into the car.
How do i set up P3 to deliver this outcome???
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?