Scheduling without disturbing ES

Umer MehmoodMember for 18 years 4 months
Created
1
22
0
Hellow to all

My name is umer ,i am working as planning engineer as a planning engineer in Descon.
I want to schedule the plan to current date suppose 12 aig,but some activities are starting in january ,and i hvenot enter progress on them.
I still that they maintain their start and End Dates.
Can any one help me in this regard
I will be thankfull to him

1 reply

Oldest first
  1. 0
    Omar Grant ·
    Hi Umar - you should save the original schedule as a target schedule. Changing the data date from the target will naturally move early starts (ie work that has not started) to the data date. However, with the target schedule shown as a bar/dates you will see the comparison of your current schedule ES to the target schedule ES. Hope this helps.

Log in or join to reply