Actual Quantity This period

Jacob MannukadenMember for 18 years 1 month
Created
1
1
0
What time frame does P3 use to Compute "Actual This Period" from Data date in Cost control Tabular reports. is this 1 Week, 1 Month or last Data Date update to currrent data date update? Or is it definable any where?

1 reply

Oldest first
  1. 0
    Pranab Kumar Deb ·
    Hello Jacob,
    Your question is not clear.

    Check rules @ Tools > Options > Autocost Rules .

    The time frame will surely be your UPDATE period i.e. when you update your schedule weekly, monthly ..... ,

    Definable obviously unless you are using "Udate progress" feature.

    By the way how are you updating the schedule , is it by imorting or manually.

    regards

    pranab