Delete reflection project

Rick AquinoMember for 21 years 6 months
Created
5
1
0
Hi All,

How to delete or remove reflection project?

Thank you

5 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·
    Hello Rick ,
    By reflection project i assume you mean target.
    1. Remove target Tools>Project Utilities >targets , then select the target from the target column and click the " - " button, click ok .

    2. Then go to Tools>Project Utilities > Delete , select he correct project and delete it.

    HTH

    Pranab
  2. 0
    Rick Aquino ·
    Thank you Pranab, however, i’m talking about P6, how to delete "reflection" in P6.
  3. 0
    Arnold Puy ·
    Hi Rick,

    To delete Reflection, go to Projects --> select the reflection project you wanted to delete and right click and select delete.

    Regards,

    Arnold
  4. 0
    Rick Aquino ·
    Hi Arnold,
    Yes i did! but the "delete" word is not highlighted, that is why i cannot delete the reflection.

    Best Regards
  5. 0
    Arnold Puy ·
    Hi Rick,

    You mean the "Delete Command" is Locked? I assumed that your project is in "Checked Out Status". Try to change to Checked In Status.


    Regards,

    Arnold