Independent activity

Moutaz AldeibMember for 22 years 9 months
Created
3
1
0
Dear Planners,

I convert a project from MS Project to P3, but when it is converted to P3, I found that all activities are independent, is there anybody know why?
Anyway, I used global change to change it to task.

Regards,

Moutaz

3 replies

Oldest first
  1. 0
    Moutaz Aldeib ·
    Is there any response?

    regards,

    Moutaz
  2. 0
    Paul Harris ·
    By default activities are "Independent" in MSP. That is when a resource is assigned to an activity then it will acknowledge the resource calendar, unless one checks the "Do not acknowledge resource calendar box". MSP does not have a equivalent to a Meeting task so they are often correctly imported as Independent. But as there are so many ways of importing a MSP schedule into P3 I am not sure they all treat the tasks the same way.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  3. 0
    Moutaz Aldeib ·
    Thanks Paul for the explanation.

    Regards,

    Moutaz