Skip to content

Problem with target bar / baseline

Mike LyonsMember for 19 years 7 months
Created
1
1
0
Hi, I am currently using a target bar to show how are activities are progressing against a baseline programme / target. However, since my last re-baseline i have had the following problem:

Whenever i update the schedule, the target bar copies the programme bar. For example, if an activity was due to finish Friday but is finished today the target bar will also move to show it should of finished today!

Any help guys would be much appreciated!

Mike

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi,

    Check out this link:

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=49596

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?