How to calculate Planned % progress in P6
In the Open Standard
Shahzad AhmadMember for 18 years 8 months
- Created
- 1
- 2
0
Dear Planner
I am use to calculate Planned % Progress through P3 ( update progress calculate by primvera) based on week / month. this time i am using P6 calculating Planned % in same way .but it is shwing only over all projetcs.( becouse P6 do not have option for bands sub-total)
WBS like
Engineering ( I need Engineering Planned % on week basis)
10 activity under engineering
Procuremnet ( I need procurement Planned % on weekly basis)
12 activity under proc.
Construction(I need construction Planned % on weekly basis)
20 activity under constr.
Commissioning.( I need comm. Planned % on weekly basis)
8 under...
In P3 there is bands shows sub total. of enach bands like Engg.,Procur, Const. Comm. however in P6 shaws only over all subtotal. Please help me out and give an idea about it. Thanks & many RegardsShahzad Ahmad
I am use to calculate Planned % Progress through P3 ( update progress calculate by primvera) based on week / month. this time i am using P6 calculating Planned % in same way .but it is shwing only over all projetcs.( becouse P6 do not have option for bands sub-total)
WBS like
Engineering ( I need Engineering Planned % on week basis)
10 activity under engineering
Procuremnet ( I need procurement Planned % on weekly basis)
12 activity under proc.
Construction(I need construction Planned % on weekly basis)
20 activity under constr.
Commissioning.( I need comm. Planned % on weekly basis)
8 under...
In P3 there is bands shows sub total. of enach bands like Engg.,Procur, Const. Comm. however in P6 shaws only over all subtotal. Please help me out and give an idea about it. Thanks & many RegardsShahzad Ahmad
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?