how to unstatus a project in P3

Richard DayMember for 18 years 3 months
Created
2
1
0
Can someone give me the steps on how to do this with global change.

I am unsure of which I do first.

2 replies

Oldest first
  1. 0
    Paul Harris ·
    Richard

    It goes something like this

    AS EQ ""
    AF EQ ""
    PCT EQ 0
    OD EQ RD

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au

  2. 0
    Sajid Balma ·
    Absolutely, but with a minor change....

    There should be a space between the quotes to run this Global Change. Else it keeps giving you Invalid Data error.

    Regards