Link between Progress and Unit Resource

Daniel SitumorangMember for 23 years 1 month
Created
0
2
0
Hi,
is it possible to break the link between ’% schedule complete’ and ’actual this period units’ for calculating the remaining units & costs of resources, then use the ’% physical complete’ as the driving factor in P5/P6?.
Thanks.

Daniel T. S