Can’t edit Activity ID numbers?

David BallMember for 19 years 2 months
Created
2
1
0
Hi all,

I have two schedules in P3. In one, I can click on an Activity ID then edit it to change the number.

In the other, the Activity IDs are greyed out when I select them and I am not able to edit them.

Any ideas on how I can set up the second schedule so that I can edit Activity IDs?

Thanks a lot.

2 replies

Oldest first
  1. 0
    Ferdinand U. ·
    open the project as exclusive (check)

    or edit the p3.ini

    As per P3 help:

    To edit activity IDs

    Enter a zero (0) on the ExclForActIDEdit line in the [Options] section of the P3.INI file to allow editing of activity IDs without exclusive access:

    ExclForActIDEdit=0

    To require exclusive access to edit activity IDs, change this line to ExclForActIdEdit=1.
  2. 0
    Johny Kesserwany ·
    In order to edit an Activity ID, the project must be open in exclusive mode.

    To open a project exclusively,

    1. Go to File, Open
    2. Highlight the project
    3. Mark the Exclusive checkbox
    4. Click Open.

    ____________________________________________________

    How to bypass Exclusive Access to edit Activity IDs:

    Open the P3.INI file by going to Start, Run and type P3.INI.

    In the Options section edit the following setting

    [Options]
    ExclForActIDEdit=0



Log in or join to reply