how to monitor cost in hammock activity???
In the Open Standard
Nizam ShukkurMember for 21 years 2 months
- Created
- 2
- 2
0
Help me. I have listed 14 hammock activities in the schedule and have loaded the cost as a resource.
I have updated the schedule.
When i view the tabular report for the cost it does not show the actual cost completed so far but instead distributes the total cost of the project from the data date till the end of the project.
Can someone help me in finding the actual cost completed using this hammock activities
I have updated the schedule.
When i view the tabular report for the cost it does not show the actual cost completed so far but instead distributes the total cost of the project from the data date till the end of the project.
Can someone help me in finding the actual cost completed using this hammock activities
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?