Activity ID
In the Open Standard
MA
Moutaz AldeibMember for 22 years 10 months
- Created
- 16
- 48
0
16 replies
Oldest first- 0FFFerdinand Fincalero, PMP ·Hi Mr. Moutaz,
Here’s a script from the help content of P3:
"The Activity ID tab enables you to classify activity IDs in ways that are meaningful within your project. For example, in a project that is part of a group, the first two characters of each activity ID are reserved for the SUBP (Project ID) code; this enables you to sort and summarize activities based on these codes.
Activity IDs can contain up to 10 alphanumeric characters, which can be divided into a maximum of four codes. Activity ID codes can be used for organizing and filtering data in the layout and in tabular reports and graphics."
Activity ID denotes a particular activity in your program, while the Activity Code refers to the coding system of your Activity ID for its usefulness as explained above.
Hope it explains its difference.
Regards,
Ferdinand - 0AFAlexandre Faulx-Briole ·As Ferdinand said in 1st place,
you can use the Activity ID tab to create a prfix that will come in front of the automatic Activity Number
have a look at the APEX master project in P3 examples to see what Ferdinand and I mean
you can also use the Activity Alias to consolidate several Activity Codes together
Alexandre - 0FFFerdinand Fincalero, PMP ·Hi Moutaz,
As per the P3 help, may I just reiterate a line in my previous posting, "Activity ID codes can be used for organizing and filtering data in the layout and in tabular reports and graphics." I think that’s the whole point of that Activity ID Tab in relation to the Activity codes.
Try to have some exercise to know more on how it goes.
Regards,
Ferdinand - 0DWDieter Wambach ·Moutaz
Activity ID is an identifier and must be unique. To address a specific activity, you’ll have to do it by the ID.
Code is is a classification and identifies a group of activities. An activity may be classified by: Construction phase, compressor A, area B7, responsibility sub "XX". Later in reports you can analyze by area, phase, responsibility, equipment.
There is a speciality for P3 because it was written a time when harddisk space and memory was extremely expensive: Out of the activity id you can use up to ten digits for four codes where the first two are reserved for the project id.
Was this an answer to your question?
Dieter - 0MWMuhammad Waqas Zafar ·Dear Moutaz,
I exactly understand what’s ur confusion is. The Activity ID tab adjacent to the Activity Codes tab can only be useful if you know and using import/export feature available in primavera.
In import/export feature one can import/export data on x-cel sheet in DBF or WK1 ....etc formats.This is done by the intelligence building of Activity ID’s on x-cel sheet and configuring the ID’s in Activity ID tab that when you import data in p.3 all the activities fall in relevant heads.When you are using import feature than you don’t need Actvity codes to build.
Its appearing complex but once you have learned how to do it !than you may never use Activity Code approach.If you need to ask more; do please let me know.
Regards
Waqas - 0EGErnani Garena ·I want to learn and understand the process in import and export data from excel to p3 & vice versa. Can you email me the step-by-step process. I would like to explore more P3 since I am new with planning.
My email address is ernan0518@gmail.com
Thank you very much in advance! - 0MWMuhammad Waqas Zafar ·Dear Ernani,
I have mailed you three seperate mails having three steps to understand import/export featuer with help of small example.Please note that:
You must install MS-xcel 2003 in your computer as no other X-cel will take that
Please dont open mail of next step until you undersatnd previous
Regards
Waqas
Log in or join to reply