Suspending an activity

Efren LabayMember for 19 years 9 months
Created
1
1
0
Hi P3 Masters,

Here is my question, i have a detailed schedule and one activity say activity ’A’ has a orig duration of 20 days. It starts and after 5 days with 20 percent completion some problems happened were the consultant ask to suspend this activity. After 10 days problems was solve thus activity resumes but again after 7 days with 60 percent completion another problem happened and it must be suspended again but P3 allows one time suspension only, it is loaded with wt. % and resources, so what is the best way to do in P3 scheduling without affecting BCWS and BCWP.


Thanks...

1 reply

Oldest first
  1. 0
    Pinan T. ·
    try to put a separate calendar for this activity w/ specified nonwork as holidays just to show the suspension of work

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?