Resource Loading in P3
In the Open Standard
Mohammed MujtabaMember for 18 years 1 month
- Created
- 5
- 1
0
Dear Planners,
Recently i revised my schedule and in that revision i deleted some activities and added some activities,, Finally the Budgeted Quantity(Mhrs) exceeded to 53000 (the previous was 50000)
After running resource loading, i added up all the Budgeted quantity (mhrs)and it came around 52000.
The remaining 1000 are missing.
WHY ?????
Pls help
Recently i revised my schedule and in that revision i deleted some activities and added some activities,, Finally the Budgeted Quantity(Mhrs) exceeded to 53000 (the previous was 50000)
After running resource loading, i added up all the Budgeted quantity (mhrs)and it came around 52000.
The remaining 1000 are missing.
WHY ?????
Pls help
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?