Resource Loading in P3

Mohammed MujtabaMember for 18 years 1 month
Created
5
1
0
Dear Planners,

Recently i revised my schedule and in that revision i deleted some activities and added some activities,, Finally the Budgeted Quantity(Mhrs) exceeded to 53000 (the previous was 50000)

After running resource loading, i added up all the Budgeted quantity (mhrs)and it came around 52000.

The remaining 1000 are missing.

WHY ?????

Pls help

5 replies

Oldest first
  1. 0
    Anoon Iimos ·
    The schedule is dynamic, that’s why, whatever will come in, will consequently come out.
  2. 0
    Arnold Puy ·
    Hi Mohammed,

    In TOOLS --> TABULAR REPORTS --> LOADING, under the Format Tab try to check your "Column Width" if it is 5 change it to the maximum of 15 & RUN.

    Try this.

    Regards,

    Arnold
  3. 0
    Azeem Abdul ·
    Yeah arnold,

    When i am running the program finally the error messeage i am getting as unexpected file format showing..?

    Plz do this solution.

    Thanks
  4. 0
    Arnold Puy ·
    Hi Azeem,

    Did you install the P3 3.1 Service Pack "P331SrvPk3.exe"? Try to install this. or you can download here:

    http://www.projectstatus.com/pub/


    Arnold
  5. 0
    Azeem Abdul ·
    Yeah it is actaully installed by the company in the same format. But dont know Y this error message is displaying.
    Do U have any alternate solution for it...?

    Thanks