MAXIMIUM ACTIVITY IN P3.1

Joseph Erwin Cargason, C.E.,PSPMember for 20 years 5 months
Created
4
1
0
Hi guys, i just want to as if what is the maximum activity that we can make in p3.1

thak you and best regards,

4 replies

Oldest first
  1. 0
    Tommy Nug ·
    I used to make a schedule with over 30,000 activities, and it’s still good.
    Cheer,

    Tom
  2. 0
    A D ·
    I have seen programs upto 90000 activities and i have personally done programs upto 44000 activities. Problem is, u can view a maximum of 32000 activities in a layout.
  3. 0
    Joseph Erwin Cargason, C.E.,PSP ·
    90,000? wow thats a big project..anyway thank for the reply guys..i appreciate it.

    Thank you and Happy new year to All
  4. 0
    Alexandre Faulx-Briole ·
    Hi Planners,
    Happy new year all
    I remember that on this forum somebody working in Khazakstan or somewhere in Central Asia said he was working on a 150000 task schedule
    No problem, he said
    Alexandre