Can not change duration in MSP
In the Open Standard
Tommy NugMember for 18 years 11 months
- Created
- 3
- 1
0
Hi buddies,
I have problem in changing duration in MSP. I converted P3 schedule to Ms Project using mpx function and adjust the schedule in Ms Project. However, most of tasks is zero duration (milestone) to revise it correctly, maybe some problems due to converting. Tried to go to Project\ Task information and choose Advance tab. Uncheck the function ’MARK TASK AS MILESTONE’, and change duration. Finally click OK but it does not change anything.
Could you help?
Thanks,
Tommy
I have problem in changing duration in MSP. I converted P3 schedule to Ms Project using mpx function and adjust the schedule in Ms Project. However, most of tasks is zero duration (milestone) to revise it correctly, maybe some problems due to converting. Tried to go to Project\ Task information and choose Advance tab. Uncheck the function ’MARK TASK AS MILESTONE’, and change duration. Finally click OK but it does not change anything.
Could you help?
Thanks,
Tommy
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?