Create an S-Curve based on Sched % Comp in P3 v3.1?

John RogersMember for 22 years 10 months
Created
2
2
0
Dear all,

I would very much appreciate some help...

I am trying to produce an S-Curve based on Schedule % Complete, based against by target programme. Both programmes are resource loaded.

Many Thanks

Regards,

John R

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear John,

    Go to Display screen,
    Select
    Type = cost
    Timer Interval = Months
    Remove check from Histogram
    Select Total from "Resource Profile/ table"

    Then you can select what you want to see for each resource or for all.

    Best,

    Samer
  2. 0
    John Rogers ·
    Excellent, thanks very much for your help Samer. Much appeciated.