Planned % comp based on Late dates.
In the Open Standard
Muhammad AliMember for 22 years 1 month
- Created
- 7
- 4
0
Friends!
I am monitoring progress based on “Duration”. I want to draw a set of S curves in X-cel (Early and Late) for the planned progress % comp based on duration.
To get early planned % comp > I use Automatic update (Control F9) run the progress on weekly basis (repeatedly). The program activities are run on all early dates and summarization based on duration gives me overall planned % comp.
Coming to the exact querry. . Is there any way to get planned Late % comp. Like any option which makes Automatic update to start all the activities on their late dates, so that I can have planned Late % comp. !!
Thanx
I am monitoring progress based on “Duration”. I want to draw a set of S curves in X-cel (Early and Late) for the planned progress % comp based on duration.
To get early planned % comp > I use Automatic update (Control F9) run the progress on weekly basis (repeatedly). The program activities are run on all early dates and summarization based on duration gives me overall planned % comp.
Coming to the exact querry. . Is there any way to get planned Late % comp. Like any option which makes Automatic update to start all the activities on their late dates, so that I can have planned Late % comp. !!
Thanx
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?