Hi
can a resource quantity for an activity set as multiply (such as 0.2 ) of another resource quantity assigned to activity

2 replies

Oldest first
  1. 0
    David Kelly ·
    Yes, but you need to use Excel. Global Change cannot use two records at a time.

    You need to export the current resource asignments, and do the manipulation in Excel before importing the spreadsheet
  2. 0
    Masoud Rahimian ·
    thans, but resourcer Hierarchy in RBS does not helps any in this case?
    main purpose of res Hierarchy is categorization to view?

Log in or join to reply