long activity description

Faik UlkuMember for 17 years 6 months
Created
7
2
0
how can i enlarge the quantitiy of the letters for activity description. for example i would like to write a description which has hundred letters.
thanks

7 replies

Oldest first
  1. 0
    Alex Wong ·
    Hi

    In P3 .... quick answer is No you cannot
    In P6 .... put your description in the notebook

    HTH

    ALex
  2. 0
    Faik Ulku ·
    thank you Alex. It is strange.
  3. 0
    Safak Vural ·
    Dear Faik,

    If you can divide the description in parts in a logical way, then you can add a activity code for the un-fit parts of the description and then you can show on the bar chart view as the columns next to activity description. Or you can add Logs to the activities.

    Regards,

    Safak
  4. 0
    Faik Ulku ·
    Dear Safak

    The problem is we have to present our schedules in both languages in Russian and English. I use log for russian part but log is also not enough for russian translation. that is the problem.
  5. 0
    Safak Vural ·
    Dear Faik,

    You can add 2 or 3 custom data items as RUS1 and RUS2. Every item will give you 20 characters to add. If you want to show in reports you can show in layout view or in other reports. It will be easy for you just to import the descriptions.

    EX:
    RUSS1-FLOOR RUSS2-BLOCK RUSS3-WORKTYPE (depends on your WBS)

    Safak
  6. 0
    Faik Ulku ·
    Tesekkur Safak Kardesim. Ellerine saglik
  7. 0
    Safak Vural ·
    Sen sagol. Basarilar.

Log in or join to reply