Storing Period Performance

Adekunle ArisilejoyeMember for 18 years 6 months
Created
3
1
0
Could someone explain this statement in more explicit terms pls.

If you store period performance, P3 spreads resource expenditures evenly for each update period and spreads expenditures for the current period from the last close out date to the data date. If yoou do not store period performance, P3 spreads resource expenditures evenly from the resource start through the data date

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Bobo,
    by using "store period performance", you know how much you have worked and spent since the last update
    I do not think it is usefull for the project period before the last update
    let’s say you update your project every monday and today is saturday: "Actual this period" displays actual work and actual cost between the last two mondays; "Actual" displays actual work and actual cost since the project start
    Hope this helps
    Alexandre
  2. 0
    Adekunle Arisilejoye ·
    Thanks man.

    Cheers
  3. 0
    Safak Vural ·
    Dear Bobo,

    If you did not store at every update the situation will be like this:

    week 1: 20% progress
    week 2: 30% progress
    week 4: 40% progress

    If you did not store each. When you have a Weekly histogram for resources. Then it will show you.

    week 1: 30%
    week 2: 30%
    week 3: 30%

    Regards,

    Safak