Dear All

Would anyone be able to tell me how to set up a column to show the "Planned Percent Complete" of an activity on a given date in P3. The programme is not cost or resource loaded so it would just be the "Planned Percent Complete" of the time element of the activity that would be shown.

Any help to a new user would be gratefully appreciated.

Andy

2 replies

Oldest first
  1. 0
    Mimoune Djouallah ·
    hi Andy

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=2&Top=26361

    HTH

    mimoune
  2. 0
    Safak Vural ·
    Dear Andy,

    There are 2 quickest ways for it:

    1-Update your target schedule (or you can have a 2nd Target as a updating version) and use target percentage as a column directly.

    2-(maybe CLIENT does not want you to touch their target) If all of your resource curves are linear. You can add a custom data item as planned percentage and write a global cange for it.
    PLANED% - PLPC
    TARGET S - TS
    TARGET F - TF
    Data Date - DD

    Then PLPC=
    IF DD is less than TS THEN 0
    IF TS is less than DD is less than TF THEN (DD-TS)/(TF-TS)
    IF DD is greater thanTF THEN 100

    You need to run global change at every update.

    Regards,

    Safak