Activity limit exceeded

José Arturo Vargas HernándezMember for 17 years 6 months
Created
6
1
0
Hello, I’m new planning and I did force to install Vista in the laptop, I have an old project that charges succesfully in XP, but in Vista shows: "Activity limit exceeded", I think maybe is a setup problem, because demo projects loads fine.

Thanks and sorry for my bad english.

6 replies

Oldest first
  1. 0
    Ferdinand U. ·
    i think you are using demo p3 version
  2. 0
    José Arturo Vargas Hernández ·
    The version installed in XP and Vista is the same
  3. 0
    Ferdinand U. ·
    not sure with this, but try to run in compatibililty mode and as administrator
  4. 0
    José Arturo Vargas Hernández ·
    I tried in mode administrator, compatibility with Windows 95, 98, 2000 and XP but the problem are the same :(
  5. 0
    Safak Vural ·
    Dear Arturo,

    Please try to run P3 fix on the project. Mayebe some of the files have been corrupted. It is in the programme directory named as PFXW.EXE.

    I hope that is the problem and the solution. I am usnig P3 both on XP and VISTA (VISTA if I work at home :)). I never encounter such problems. I will look when I return home.

    Regards,

    Safak
  6. 0
    José Arturo Vargas Hernández ·
    Finally I fix the problem, I ran Windows Update, reinstall P3 and voila!!! works great.

    Thanks for your time :)